Tower Landfill Phase 2, Cell 2B, Unit 3

Owner:

Republic Services

General Contractor: 

Kelley Trucking Inc.

Contract Amount:  $2.0 M+

Mountain Lake
Beach Huts
Ferris Wheel
Palm Trees
City Cycle
Misty Slopes
Fire Wood
Foggy Pier
Cafe in Autumn
Blue Stairway
Two Flamingos
Old City Street
River Boathouse

Construction of new landfill cell including excavation of 837,300CY, 615,600SF of subgrade preparation, placement of 341,600CY of engineered fill, 77,700CY of compacted clay liner placement, construction of leachate collection system, including 11,400CY granular drainage layer and 1,860LF of HDPE piping system and temporary leachate sump pumps, placement of protective soil cover and liner termination, and installation of stormwater controls.