Eagle County Regional Airport
Owner:
Eagle County Regional Airport
General Contractor:
Kelley Trucking Inc.
Contract Amount: $18.1 M+
The Airport project including hauling and placement of 1,750,000 CY of fill material for a future 1,000 foot runway extension.
Installation of approximately 1,300 feet of 114” culvert and 7,500 SQ. FT. of MSE wall. Eagle County Airport was a challenging project due to a tight schedule which required the project to be completed between April and November due to commercial flight operations. Additionally, FAA security measures had to be maintained throughout the project.