18th and Market, Denver (Downtown)

Owner:

Milender White

General Contractor: 

Kelley Trucking Inc.

Contract Amount: $1.6 M+

Mountain Lake
Beach Huts
Ferris Wheel
Palm Trees
City Cycle
Misty Slopes
Fire Wood
Foggy Pier
Cafe in Autumn
Blue Stairway
Two Flamingos
Old City Street
River Boathouse

Excavation and export of approximately 45,000 CY of soil to construct underground parking structure for residential and commercial tower being built in heart of downtown Denver, Colorado. Project included demolition of existing lot, excavation and abatement of approximately 15,000 CY of man-made fill to a subtitle Class D landfill, and all structure excavation and backfill. Due to a higher than expected water table that typical dewatering techniques had difficulty dealing with, Milender White and Kelley Trucking were able to collaborate and come up with creative solutions to keep project on schedule and moving forward despite the wet conditions.